CleanSpark weighs Bitcoin reserve sales after $987.1 million annual loss
CleanSpark sold or delivered 394 BTC more than it mined from July to September. The Bitcoin miner says it may also sell coins from its reserves to manage price risk and fund an expansion into AI data centers.
- CleanSpark ended September 30, 2025, with 13, 530 BTC, including assets pledged or tied to derivatives.
- It sold or delivered 2, 102 BTC in the quarter and mined 1, 708 BTC.
- Fiscal 2025 revenue fell 25% to $576.5 million; the company reported a $987.1 million net loss.
- CleanSpark targets November 2027 for its first AI data hall at its Sandersville campus in Georgia.
What CleanSpark’s Bitcoin sales show
On its November 24 earnings call, CleanSpark President and CFO Gary Vecchiarelli said the company plans to sell nearly all newly mined Bitcoin to cover operating expenses. Management is also considering sales from its existing treasury, depending on market conditions and capital needs.
Those are two different decisions. Selling newly mined Bitcoin turns ongoing production into cash. Selling Bitcoin from the treasury cuts into the company’s existing holdings. CleanSpark has not said how much it might sell, when it might sell, or what conditions would prompt a sale.
The company reported holding 13, 530 BTC at the end of September. Of that total, 3, 475 BTC were either pledged as collateral or recorded as receivables linked to derivatives transactions. CleanSpark did not break down the amount in each category. Receivables tied to contracts are not necessarily Bitcoin the company holds outright, so the reported reserve total does not show how many coins are freely available.
From July through September, CleanSpark produced 1, 708 BTC and sold or delivered 2, 102 BTC, 394 BTC more than it mined, or about 23% of quarterly production. That total includes contract-related deliveries, not just sales on spot markets.
In September, the company sold 2 BTC on spot markets and delivered another 700 BTC after call options were exercised. A call option is a derivative contract that can result in an asset being delivered. CleanSpark shared no further details about the contracts, so the delivery should not be treated as a standard spot sale.
Monthly production was 586 BTC in July, 593 BTC in August and 529 BTC in September. Sales and deliveries were 579 BTC, 821 BTC and 702 BTC, respectively.
A large reported loss, but not the same as cash burn
For the fiscal year ended September 30, 2025, CleanSpark reported a net loss of $987.1 million, compared with net income of $364.5 million the previous year. Management said noncash adjustments tied to changes in the value of its Bitcoin holdings accounted for approximately two-thirds of the difference between the annual results.
Noncash adjustments affect reported earnings without necessarily representing money paid out or received. That distinction matters, but the loss still counts: operating costs, financing needs and Bitcoin price exposure affect the company’s financial position.
Fiscal-year revenue fell 25% to $576.5 million. Adjusted EBITDA, a company measure of earnings before interest, taxes, depreciation and amortization that includes adjustments, was a loss of $304.2 million. In the fourth quarter, revenue fell 46% year over year to $120.9 million. CleanSpark reported quarterly net income of $9.8 million, or $0.04 per basic share.
At the end of September, CleanSpark reported approximately $204.8 million in cash and cash equivalents and $1.13 billion in Bitcoin holdings. The company put combined year-end liquidity at around $1.3 billion, including pledged assets. That figure is a snapshot, not a promise that every asset is available without restriction.
Mining output declined as the company pursues AI data centers
CleanSpark mined 7, 253 BTC in fiscal 2025, down 8% from the prior year. Its average hashrate, the computing power devoted to mining, fell 21% to 36 exahashes per second.
The company also reported better energy efficiency across its mining fleet. At the end of September, its equipment used 14.8 joules per terahash, down from 16.7 joules at the end of fiscal 2024. Using less energy per unit of computing work can help control costs. Profitability still depends on Bitcoin’s price, electricity costs and competition across the network.
CleanSpark said its digital asset management program generated $30.6 million in proceeds from derivatives transactions during the financial year. That activity helps explain the company’s Bitcoin position: production, holdings and deliveries alone do not account for every movement in its digital assets.
The company is also developing data-center projects. At its Sandersville campus in Georgia, CleanSpark is targeting November 2027 to deliver its first AI data hall. The project is backed by a 20-year lease with an unnamed investment-grade tenant. CleanSpark expects approximately $6.6 billion in contracted revenue over the lease term. That is a projected gross revenue figure, not profit or cash already earned. Delivery and performance under the lease are still ahead.
“The completion of our Sandersville financing provides dedicated capital and fully funds the project, ” Vecchiarelli said.
CleanSpark reported raising $2.276 billion through senior secured notes with a 7.875% annual interest rate and a 2031 maturity. The company says the Sandersville project is fully funded, but its broader expansion plans are not debt-free. The notes also leave CleanSpark with a substantial financing commitment.
Plans for other data-center capacity are less certain. CleanSpark has conditional baseload designations covering 585 megawatts across its Sealy and Brazoria properties in Texas. At its Washington, Georgia, property, the company acquired 500 acres of adjacent land and submitted a transmission study seeking to raise available power capacity from 86 megawatts to as much as 500 megawatts. The conditions and timelines for those power arrangements remain unclear. Similar questions about mining companies’ AI expansions appear in coverage of IREN’s proposed pivot from Bitcoin mining to AI data centers and Core Scientific’s data-center plans.
Key questions
-
Will CleanSpark sell Bitcoin from its reserves?
Management is considering it, on top of selling nearly all newly mined Bitcoin. The company has not announced an amount or timetable.
-
Does the $987.1 million loss mean CleanSpark spent that much cash?
Not necessarily. Management said noncash Bitcoin valuation adjustments accounted for approximately two-thirds of the difference between the annual results. The loss alone does not measure cash burn.
-
Was all 2, 102 BTC sold on the open market?
No. The figure combines sales and deliveries, including derivatives-related transactions. CleanSpark disclosed a 2 BTC spot sale and a 700 BTC delivery after call options were exercised in September.
-
When could the first Sandersville AI data hall be delivered?
CleanSpark targets November 2027. The 20-year lease and projected revenue depend on a facility that has not yet been delivered.
The next useful signals will be disclosed treasury sales, cash flow and debt obligations, along with progress on power approvals and construction. The key test is whether CleanSpark can deliver its data-center plans without significantly weakening its Bitcoin position.