A $6.56 billion lease sounds like a clean break from Bitcoin mining. For CleanSpark, it’s a long-term opportunity with a long wait attached. As of Sept. 30, 2026, the company had recognized no rent from its Sandersville data center. Mining remained a major source of revenue, and Bitcoin sales helped meet cash needs.
- The lease: 20 years and 175 megawatts of critical IT load, with the first phase expected in November 2027.
- The mining business: Fiscal 2026 output and revenue fell, while energy costs claimed a larger share of mining revenue.
- The risks: Project debt, construction obligations and limits on cash transfers stand between lease payments and the parent company.
A large contract, but rent has not started
CleanSpark’s Sandersville project in Georgia is converting mining infrastructure into a data center. The 20-year lease covers 175 megawatts of critical IT load, the capacity intended for the tenant’s computing equipment, and calls for about $6.56 billion in rent during the initial term. That total excludes variable reimbursements and any extension payments.
Dividing $6.56 billion by 20 gives a simple average of about $328 million a year. That figure shows the contract’s scale, but it is not a forecast of annual receipts. Rent is scheduled to begin in phases as parts of the facility are delivered and lease conditions are met. The original deal announcement said two optional five-year extensions could raise total contracted revenue to $11.6 billion if exercised.
As of Sept. 30, 2026, CleanSpark had recognized no Sandersville lease revenue. The company had received $5 million as an advance against the first month’s rent and recorded it as deferred revenue, meaning it had received the money before it qualified as recognized rent.
The first data hall was expected to be delivered in November 2027, with phased lease commencement anticipated from November 2027 through March 2028. In a management update dated Nov. 24, CleanSpark said the first hall remained on track for November 2027 and that it had obtained material building and development permits. Those are signs of progress, not a guarantee that delivery will meet the target.
CleanSpark also expects tenant fit-out work, which prepares the space for the tenant’s equipment, to generate revenue before rent begins. The company said it can recover eligible costs and earn a management fee, but it had recognized no fit-out revenue under the arrangement by Sept. 30. Its filing treats this work as a service under ASC 606, with revenue recognized as qualifying work progresses. The actual economics and payment timing remain undisclosed.
Project financing could limit what reaches the parent
CleanSpark subsidiary CSDC Finance I issued $2.276 billion in secured notes to finance Sandersville. The notes carry a 7.875% coupon and mature in 2031. They were sold at 98.5% of face value. After the original issue discount and issuance costs, CleanSpark’s annual filing reported net proceeds of about $2.208 billion.
At the original principal, the coupon implies roughly $179.2 million in simple annual interest. That is not a full debt-service schedule. Actual obligations depend on the note terms and any principal reductions. The first interest payment was scheduled for April 1, 2027, with payments twice a year. Scheduled principal installments were expected to begin Oct. 1, 2028.
The $179.2 million interest calculation equals about 55% of the lease’s simple average annual rent of $328 million. That comparison excludes principal, project expenses and the phased rent schedule. Still, it makes one point clear: gross rent is not the same as cash available to CleanSpark’s parent.
About $327 million went into an initial debt-service reserve. At fiscal year-end, CleanSpark reported about $2.14 billion in restricted cash tied to project financing. Restricted cash comes with limits on how it can be used. It is not automatically available to fund the company’s mining operations.
The notes mature on Oct. 1, 2031, well before the initial lease term is scheduled to end in 2047. How CleanSpark will repay, refinance or otherwise settle the notes remains an open question.
CleanSpark President and Chief Financial Officer Gary Vecchiarelli said the financing “provides dedicated capital and fully funds the project.” The filing also describes a completion guarantee. If note proceeds and other available funds are not enough to finish the facility, CleanSpark may have to provide funding under the guarantee’s terms. The financing is presented as sufficient under the project plan, but the guarantee leaves the parent exposed if available project funds fall short.
The completion guarantee does not guarantee repayment of the notes. It is uncapped and, under the filed terms, ends upon full rent commencement. CleanSpark separately guaranteed construction obligations to the tenant. The tenant’s parent guarantees lease payments, subject to a cap tied to unpaid base rent and operating expenses.
Project entities face restrictions on distributions, loans and other transfers. Tenant payments must first support project expenses, debt service and reserve replenishment. Whether project cash can be distributed to the parent, and how much, will depend on those obligations and restrictions.
Mining remains central while Sandersville is built
CleanSpark mined 7, 253 BTC in fiscal 2026, down from 7, 873 the year before. Its average hashrate, a measure of computing power devoted to mining, fell 21% to 36 exahashes per second. Mining revenue declined to $576.5 million from $766.3 million.
The company reported a $987.1 million net loss, compared with $364.5 million in net income in fiscal 2025. Bitcoin fair-value results contributed to the reversal. A $425.6 million gain in fiscal 2025 became a $281.6 million loss in fiscal 2026. Based on the rounded figures reported, that’s a swing of about $707.2 million.
A fair-value loss reflects a change in the accounting value of Bitcoin holdings. By itself, it does not mean the company sold Bitcoin or spent that amount in cash. CleanSpark also reported $428.2 million in depreciation and amortization and a $118.7 million loss on Bitcoin collateral receivables among its principal cash-flow adjustments.
Cash used in operations was about $468.4 million in fiscal 2026, compared with about $461.0 million a year earlier. These are company-wide figures, not a measure of cash consumed by mining alone. They also leave out other sources and uses of liquidity, including Bitcoin sales, derivative settlements, financing and restricted project funds.
Mining costs tightened even as electricity prices eased. Electricity at owned operations averaged 5.5 cents per kilowatt-hour, down from 5.7 cents, but energy cost per Bitcoin rose about 9.9%, from $42, 890 to $47, 130. Owned-site energy expense reached about $341.8 million, roughly 59% of mining revenue, compared with about 44% the prior year.
The filing separately put direct owned-site mining costs at $47, 196 per Bitcoin. That is a different measure from the $47, 130 energy cost per Bitcoin. The former covers direct mining costs, while the latter refers to energy alone. The filing also listed miner depreciation of $52, 352 per Bitcoin. Together, direct costs and miner depreciation came to $99, 548 per coin, roughly 125% of average revenue per mined Bitcoin.
At a hypothetical Bitcoin price of $60, 000, a coin would leave $12, 804 after the stated $47, 196 in direct mining costs, before other expenses. But that price would not cover direct costs plus miner depreciation. This is an illustration, not a forecast or a reported sale price. It shows why mining margins can look different depending on which costs are included.
Bitcoin production, sales and treasury are not interchangeable
In the final quarter, CleanSpark produced 1, 708 BTC and sold or delivered 2, 102 BTC. The 394 BTC difference, about 23% of quarterly production, could include coins from the existing treasury, not just newly mined Bitcoin.
Production, spot sales and derivative deliveries are different activities. In September, CleanSpark reported selling two BTC on the spot market and delivering 700 BTC through exercised call options. A call option can require Bitcoin to be delivered at an agreed price when a counterparty exercises it. That is not the same as selling coins on the spot market at the prevailing price.
For the full fiscal year, CleanSpark reported $609.2 million in cash from Bitcoin sales and settlement of Bitcoin-linked derivatives. The combined figure is not spot-sale revenue alone. The company separately attributed $30.6 million of proceeds to derivatives activity in its fiscal 2026 release.
At Sept. 30, CleanSpark reported a treasury of 13, 530 BTC: about 11, 720 BTC held directly and a receivable for 1, 810 BTC posted as collateral. A collateral receivable is an accounting asset linked to Bitcoin pledged under an arrangement. Access to the underlying coins depends on the arrangement’s terms.
At CleanSpark’s September valuation, the directly held Bitcoin was worth about $979.3 million and the collateral receivable about $151.2 million. The collateral-related balance represented about 13.4% of the reported treasury, but it should not be assumed to be as readily available as coins held directly.
CleanSpark reported $204.8 million in cash and cash equivalents at Sept. 30, up from about $43 million a year earlier. It cited $1.3 billion in year-end liquidity, combining cash with Bitcoin valued at the September price, including collateral. The reported figures, about $979.3 million in held Bitcoin, $151.2 million in collateral receivables and $204.8 million in cash, sum to roughly $1.335 billion. That matches the rounded $1.3 billion figure.
At an illustrative $60, 000 per BTC, all 13, 530 BTC would be worth about $811.8 million. Adding reported cash gives roughly $1.02 billion, approximately $319 million below the sum of the September component values. This is a price-sensitivity comparison, not a measure of cash available to the parent. Some Bitcoin was posted as collateral, and project cash is restricted.
What to watch next
- When will Sandersville deliver its first hall and begin generating rent?
CleanSpark’s target is November 2027, with phased commencement anticipated through March 2028. No lease revenue had been recognized by Sept. 30, 2026, and the delivery schedule remains subject to construction and lease conditions. - How much of the Bitcoin treasury is readily available?
About 11, 720 BTC were held directly, while 1, 810 BTC were represented by a collateral receivable. Access to the collateral depends on the terms of the arrangement. - Can Sandersville avoid further parent funding?
That has not been established. CleanSpark may have to contribute funds under its completion guarantee if project proceeds and other available funds fall short. - What happens to the project notes in 2031?
The notes mature before the initial lease term ends in 2047. The eventual repayment, refinancing or other permitted settlement plan remains unresolved.
A promising transition with conditions attached
Sandersville could give CleanSpark a second business with long-term contracted revenue and reduce its reliance on mining alone. But the lease is not yet replacing mining revenue. Construction and delivery come first. Project debt and transfer restrictions will also shape how much cash can reach the parent.
Bitcoin remains central to CleanSpark’s finances in the meantime. Management has described an intention to sell nearly all newly mined Bitcoin to cover operating expenses, with modest sales beyond production depending on conditions. Future disclosures on production, sales and derivative deliveries will show how that policy plays out in practice.
The tests are concrete: deliver the first hall, collect rent, manage construction costs, meet project debt obligations and establish how much cash can move from Sandersville to the parent. Until then, $6.56 billion is a substantial contracted opportunity, not $6.56 billion in the bank.